Free Scrum of Scrums template: agenda, team updates and impediment log

Run a focused 15-minute Scrum of Scrums: an agenda, the three team update questions, an impediment log, a dependency list and action items. Copy the tables or download them as one Excel workbook.

No credit card required. Host your data in the EU (Germany) or the US.

What is a Scrum of Scrums template?

A Scrum of Scrums template is a ready-made agenda and set of logs for the meeting where representatives of several Scrum teams coordinate their work: a 15-minute agenda, a team update with three standard questions, an impediment log, a dependency list and action items. This page gives you all five, free, as tables and as one Excel workbook.

In Scrum@Scale the meeting is the Scaled Daily Scrum: at least one representative from each team attends, and it "is time-boxed to 15 minutes or less."[1] The templates below are built for that timebox.

Free .xlsx file, no sign-up. Works in Excel, Google Sheets and Numbers.

What is in the free Scrum of Scrums template?

The Excel workbook has six sheets: a read-me and five templates. Example rows are shaded so you can see how each one is filled in.

  • Agenda: a 15-minute agenda with who leads each part and what it produces.
  • Team updates: the same questions for every team, one row per team per meeting.
  • Impediments: what teams cannot solve alone, with an owner, next step and status.
  • Dependencies: who needs what from whom, and by which sprint.
  • Action items: decisions and follow-ups with an owner and a due date.

Scrum of Scrums agenda template

Keep the Scrum of Scrums to 15 minutes. Spend most of it on team updates, give the rest to the impediments and dependencies that need a decision, and solve problems after the meeting with only the people involved.

Scrum of Scrums agenda template for a 15-minute meeting.
MinuteItemWhoOutput
0 to 1Review open action items from last timeFacilitatorActions closed or carried over
1 to 9Team updates: impediments, impact on other teams, new dependenciesOne representative per teamUpdated impediments and dependencies
9 to 13Impediments and dependencies that need a decisionFacilitatorAn owner and next step for each
13 to 15Confirm action items and ownersFacilitatorAction list for next time
After the meetingProblem solving with only the people involvedOwnersResolved or escalated items

Scrum of Scrums team update template

Every team answers the same three questions, taken from the Scrum@Scale Guide, so updates are short and comparable.[1]

Team update template with an example row.
QuestionExample answer from Team Alpha
What impediments put our Sprint Goal or delivery plan at risk?Test environment unavailable since Tuesday
Are we doing anything that may block another team?Changing the payments API schema in sprint 3
Have we found a new dependency, or a way to resolve one?Team Beta must update its client by sprint 4
Progress against the goalOn track for the sprint goal

The Scrum@Scale Guide describes the meeting as "a forum to discuss how teams can work together more effectively, what has been done, what will be done, what is going wrong & why, and what the group is going to do about it."[1]

Impediment log template

Log only the impediments a team cannot remove alone. Each one needs an owner and a next step before the meeting ends, and stays on the list until it is resolved.

Impediment log template with an example row.
ImpedimentTeamImpactOwnerNext stepStatus
Test environment unavailableTeam AlphaBlocks testing for 2 storiesPlatform leadRestore and confirm by ThursdayOpen

Dependency template

Record each dependency with the team that needs it, the team that provides it and the sprint it is needed in, and review the list at every Scrum of Scrums.

Dependency template with an example row.
What is neededNeeded byProvided byNeeded inStatus
Updated payments API clientTeam BetaTeam AlphaSprint 4Committed

For mapping dependencies across a whole release train, read the dependency management guide.

Action items template

Close every meeting by reading back the action items with their owners and due dates, and open the next meeting by checking them.

Action item template with an example row.
ActionOwnerDueDone
Ask the platform team for a test environment ETAFacilitatorNext meetingNo

How does a Scrum of Scrums work in SAFe?

In SAFe, "the ART Sync consists of two main, synchronized conversations that are typically combined into a single event: The PO Sync and the Coach Sync."[2] The Coach Sync brings Scrum Masters or Team Coaches together on progress, dependencies and impediments, which is the role a Scrum of Scrums plays, so the same templates work for it.

The ART Sync is described as "the primary mechanism for the ART to align during the PI."[2] Use the dependency list from your PI Planning template as the starting point, so the Scrum of Scrums tracks what the teams committed to.

When does a spreadsheet stop working for Scrum of Scrums?

A spreadsheet is fine for a few teams. It gets harder when updates are spread across files, when nobody follows up on action points between meetings, and when impediments and dependencies have to be matched to the real work in Jira or Azure DevOps.

The Kendis Scrum of Scrums feature keeps highlights, impediments, progress updates and action points in one place for Scrum Masters, with reminders for each team and virtual room links, on the same board as your program board and dependencies.

Scrum of Scrums highlights and impediments in Kendis
The Scrum of Scrums in Kendis: highlights and impediments per team in one place.

Run your Scrum of Scrums in Kendis, free for 6 months

Kendis is a PI Planning and tracking platform that sits on top of Jira and Azure DevOps. The free trial runs for six months, long enough to plan and track two full PIs with your real backlog before anyone has to approve a budget.

  • 6 months free, no credit card
  • Choose EU hosting (OVHcloud, Frankfurt) or US hosting (AWS)
  • Planning board, dependencies, PI objectives, ROAM risks, solution boards
  • Two-way sync with Jira Cloud, Jira Data Center and Azure DevOps
  • ISO/IEC 27001 certified, GDPR compliant, DORA Schedule available
  • No user caps and no setup costs during the trial

One trial per organisation that has not used Kendis in the last twelve months. After the trial, Premium Cloud is $14 per user per month billed annually, or $16 monthly, and you license only the people who plan. SSO, Kendis AI and premium support are part of paid plans. See pricing and the free trial terms.

More templates and guides

Scrum of Scrums template: frequently asked questions

Is there a free Scrum of Scrums template?

Yes. This page has a free Scrum of Scrums agenda, team update, impediment log, dependency list and action item template, as tables and as one Excel workbook with no sign-up.

What is the agenda of a Scrum of Scrums?

Review open action items, take a short update from each team on impediments, impact on other teams and new dependencies, decide owners for what needs a decision, and confirm action items. Problem solving happens after the meeting.

How long should a Scrum of Scrums be?

The Scrum@Scale Guide timeboxes the Scaled Daily Scrum to 15 minutes or less.

Who attends a Scrum of Scrums?

At least one representative from each team, often the Scrum Master or a team member who knows the work, plus a facilitator such as a Scrum Master or the Release Train Engineer.

What questions are asked in a Scrum of Scrums?

What impediments put a team's Sprint Goal or delivery plan at risk, whether a team is doing anything that will block another team, and whether any new dependencies, or ways to resolve one, have been found.

What is the Scrum of Scrums called in SAFe?

In SAFe the coordination happens in the ART Sync, which combines the PO Sync and the Coach Sync. The Coach Sync covers progress, dependencies and impediments across teams.

Sources

Every external claim in this guide links to the primary source below. All links were checked on 19 October 2026.

  1. Scrum Inc. The Scrum@Scale Guide, version 2.1 (February 2022).
  2. Scaled Agile, Inc. ART Sync.

The meeting structure and questions follow the Scrum@Scale Guide, and SAFe terms follow Scaled Agile's published pages, linked above. The agenda timings and example rows are Kendis examples to adapt. If something is out of date, tell us and we will correct it.

Keep every Scrum of Scrums in one place

Kendis is free for six months with no credit card. Track highlights, impediments, dependencies and action points next to your program board, synced with Jira or Azure DevOps.

No credit card required. EU or US hosting. See pricing and what the trial includes.